Elliot Road and Signal Butte Road Improvement Projects

Print
Press Enter to show all options, press Tab go to next option

Elliot Road Waterline - Sossaman to Signal Butte Road

Project Details

Kinkaid Civil Construction has been awarded the project to construct improvements to the water transmission system in the southeast valley. The contractor will construction a new 42-inch waterline along Elliot Road from Signal Butte to Hawes Road. From Hawes Road to Sossaman, the contractor will install a 30-inch waterline. This new waterline will distribute water from the new plant being construction at the northeast corner of Signal Butte and Elliot Road. 

This project is critical to support the City of Mesa planned growth in the southeast Mesa area. The Falcon Field Transmission Main (new waterline) will provide water supply from the Signal Butte Water Treatment Plant that is currently under construction.

Project Schedule/Updates

UPDATE: October / November, 2017

Construction began the week of March 6, 2016.  Crews are currently installing 42" waterline from Hawes to the east. To date they have installed almost 9,500 feet of pipe!

Next Up....

The contractor anticipates completing the work between Hawes and Ellsworth Road by the end of November, 2017. What this means is the majority of the barricading will to be removed!  

 

CAP Raw Water Pipeline Project

Project Details

Garney Construction was awarded the Construction Manager at Risk (CMAR) to install a 54-inch pipeline that will extend along Elliot Road from Signal Butte Road to the east for approximately three miles. This pipeline will ultimately provide up to 53 million gallons of water per day to the Signal Butte Water Treatment Plant.

Project Schedule/Updates

UPDATE: October / November, 2017 

Garney Construction is really making progress! To date, they have installed almost 14,000 feet of 54” pipe (that’s over two miles of pipe)!

NEXT UP…

Over the next several weeks, crews will continue pipe installation east on Elliot Road towards Meridian Road.  After Thanksgiving, crews will be on-site replacing portions of the new sewer line on Elliot Road east of Ellsworth Road. Meridian is scheduled to be CLOSED south of Elliot Road from October 30th through November 10th.

Restrictions Elliot Road and Signal Butte Road

Restrictions on Elliot from Signal Butte Road to Meridian

If you have any questions, please contact Rene Powell or Michele Arrollado at 480-644-3800.