Elliot Road and Signal Butte Road Improvement Projects

Print
Press Enter to show all options, press Tab go to next option

Elliot Road Waterline - Sossaman to Signal Butte Road

Project Details

Kinkaid Civil Construction has been awarded the project to construct improvements to the water transmission system in the southeast valley.

Project Schedule/Updates

UPDATE: May, 2018 / June, 2018

Construction began the week of March 6, 2017 and is nearing completion! Crews have completed the installation of the 42" waterline from Ellsworth Road to the east (over 20,000 feet of pipe installed for the entire project)! Next they will make the connection in the intersection of Signal Butte and Elliot Road. Once the connection has been made, the contractor will complete paving and property restoration.

NEXT UP....

Crews are on-site testing the newly installed waterline. Once all the testing has been completed, the barricading will be reduced. The contractor is continuing working on miscellaneous items such as property restoration, punch list items, etc.

CAP Raw Water Pipeline Project

Project Details

Garney Construction was awarded the Construction Manager at Risk (CMAR) to install a 54-inch pipeline that will extend along Elliot Road from Signal Butte Road to the east for approximately three miles. This pipeline will ultimately provide up to 53 million gallons of water per day to the Signal Butte Water Treatment Plant.

Project Schedule/Updates

UPDATE: May, 2018 / June, 2018

Garney Construction is really making progress - all underground piping on the first phase of the project has been completed! Crews will begin the next phase of the project next week.

NEXT UP… 

The contractor has begun the second phase of this project - the Elliot Road Improvements portion. This phase includes roadway work, new medians and sidewalks with miscellaneous landscaping on Elliot from Signal Butte to Meridian Road. 

April 9, 2018 through mid-July, 2018 - Elliot Road will be restricted to one lane in each direction from Signal Butte to Oxley for roadway improvements.  Left turns will be maintained at the intersection of Elliot and Signal Butte Road.   

A new park is planned for the area east of the new Water Treatment Plant on the northeast corner of Signal Butte and Elliot Road. The City hosted a public meeting on December 13,2017 allow residents to view renderings of the proposed amenities. Below is a link to view the renderings that were presented at the meeting.

Park Concept Plans

If you have any questions, please contact Rene Powell, Michele Arrollado or Lucy Lopez at 480-644-3800.