Bridge Safety Rehabilitation

Project Number 11-916-601


 

Project Updates

12/24/2012

 

The City of Mesa has awarded this project to Goldie Construction Inc

Project completed.





Project Schedule

 

Construction on this project began in September 2012 and was completed in December 2012.

Project Details

 

The bridges in Mesa are inspected on a bi-annual basis with safety improvements and maintenance items noted in the inspection reports. This project is the second of three projects that will address these items, along with implementing other pedestrian safety railing improvements at the bridges.

This project includes approximately 360 feet of new pedestrian safety railing 80 feet of new guard rails, 5000 square yards of bridge deck protective sealant and miscellaneous maintenance safety improvements for 26 bridges over SRP Canals throughout the City.


Project Funding

The recommended total award amount for this project is $206,910, based on the low bid amount of $188,100 plus an additional $18,810 (10% allowance for change orders).  Funding is available from the FY 12/13 Transportation Operating Budget.