Re-Drill of City Well No. 14

Project Number 05-056-004


 

Project Updates

11/19/2012

 

The City of Mesa has awarded this project to Zim Industries Inc

The contractor is doing final clean up





Project Schedule

 

This project started end of June 2012 and will finish up at the end of 2012.

Project Details

 

The City of Mesa maintains and operates numerous groundwater wells throughout the City to provide drinking water for Mesa citizens.  This project will replace an existing well located in downtown Mesa, which has deteriorated and become unusable.

City Well No. 14 was originally drilled in 1964.  In 2007, a video examination was completed on the existing well and it was determined that the well casing had deteriorated to the point that the well could not remain in service.  This project will properly abandon the existing well and drill a new well on the adjacent lot (652 S. Horne) to the south that was purchased in 2010.  Equipping of the well for pumping into the water system will be completed with a future project once the well is drilled and the well pumping rate is determined.


Project Funding

 

The recommended total award of this project is $1,059,454.00, which consists of a low bid of $963,140.00 plus an additional $96,314.00 (10% allowance for change orders).  This project will be funded from the FY 11/12 Water Bond Capital Program.