Pressure Reducing Valve Station 36 at Val Vista Treatment Plant

Project Number 10-473-001


 

Project Updates

02/04/2013
 

The City of Mesa has awarded this project to SWABS-AZ Inc

Project is complete.

Project Schedule

Construction on this project is scheduled to begin in August 2012 and is estimated to be completed in February 2013.

 

Project Details

 

The City’s 2004 Water Master Plan identified the need for a PRV to be located at North Val Vista Drive and the South Canal to be able to transfer water from the Falcon Field Zone to the Northeast City Mini Zone to support pressures in the Citrus Heights area, north of McDowell Road between Gilbert Road and Val Vista Drive during peak demand periods.  With the construction of the Lehi Crossings development to the north, and the subsequent increase in demand, the PRV will provide a redundant water feed to the Northeast City Mini Zone, in addition to improving fire flow capabilities.  During Salt River Project (SRP) dry-up events, when operation of the Northeast City Mini Zone Pump Station is not recommended, the PRV will provide a way to deliver water to the Northeast City Mini Zone along with PRV 26.

This project will construct a new PRV station that will be within a masonry enclosure located on the Val Vista Water Treatment Plant property that is jointly owned by the cities of Mesa and Phoenix.  It will be located outside of the plant security perimeter with access for our employees from N. Val Vista Drive.


Project Funding

 

The total award amount is $231,577.20 comprised of the lowest base bid of $210,524.73 plus $21,052.47 (10% allowance for change orders).  Funding is available in the FY 11/12 Water Bond Capital Program.