Pecos Road Sulfide Station

Project Number 01-685-001


 

Project Updates

02/04/2013

 

The City of Mesa has awarded this project to Blucor Contracting Inc

All contract work is complete.





Project Schedule

 

Construction on this project began at the end of April 2012 and is scheduled to be completed by the mid of December 2012.

Project Details

 

The existing Pecos Road Sulfide Control Station (SCS) was installed in 1991.  This station was designed to inject ferrous chloride into a wastewater lift station located on the same site.  In 2005, an 18” sewer was installed in Ellsworth and Pecos Roads to convey the wastewater flow previously pumped to a gravity sewer line located approximately seven miles away.  At that time, the SCS was modified to discharge to the new Pecos Road sewer to help control odors in that line.  The SCS remained in service until 2009, when it reached the end of its service life.   In 2009, an Odor Control Master Plan prepared for the Utility Department identified odor sources along this line to still be problematic and required an upgrade of the system.

The existing SCS facility was designed to control odors in the original lift station wet well only and was not sized to provide additional odor control in the Power Road and Germann Road sewers.  In addition, the existing equipment is 20 years old and requires complete replacement.  This project will demolish the original lift station and sulfide control station and replace the SCS with an upgraded facility that is specifically designed to meet the needs of the existing wastewater flows in the downstream collection system and that meets current City design standards.


Project Funding

 

The recommended total award amount for this project is $1,018,083.00, based on the lowest bid of $925,530.00 plus an additional $92,553.00 (10% allowance for change orders). Funding is available in the FY 11/12 Wastewater Capital Bond Program.