Power Road Improvements Pecos Road to Santan Freeway
Project Number 07-066-001


 

 

Project Updates

 

05/21/2013

The City of Mesa has selected Haydon Building Corp. as the Construction Manager at Risk (CMAR) for this project. This project has been split into two Guaranteed Maximum Price (GMP) projects. There is still work included in GMP #1 that needs to be completed to coincide with the Roosevelt Water Conservation District's (RWCD) dry up period. The work in GMP #2 includes the majority of the road work and began on June 18, 2012.

GMP #2 -  The new northbound roadway grading continues from Old Pecos Road to north of Williamsfield Road. Northbound ABC haul in  and fine grading was completed from Old Pecos Road north to the south well site. Base asphalt paving in this section will be paved this week. Crews started to pour streetlight pole foundations and install conduit north on Power Road north of Ray Road for the City of Mesa. The fiber optic sleeve and conduit was installed at the Power Road EMF bridge south of Williamsfield Road. Channel excavation and haul will continue throughout this week and first part of next week. Storm drain crews are installing pipe 18 inch and 36 inch storm drain continues to be installed on the east side of Power Road north of Gavelston.

 

The Northbound RWCD bridge deck was poured on Wednesday May 1, 2013 and continues to cure under blankets placed over the deck. The northbound EMF bridge pier cap 3 and abutment 2 were poured and stripped last week. The subcontractor completed the demolition of existing sidewalk and barrier wall on the Williamsfield Road EMF bridge. Work is also taking place at various wall structures through out the project.

Traffic Restrictions:

Williamsfield Road (north side) will be down one lane in each direction, from Power Road east to the round-about.  All travel lanes will be on the south half of the roadway.

Traffic shifted to new southbound alignment from the south split to Pecos Road with barricade edge lines for north and southbound. Concrete barrier installed over the double barrel box culvert.

Flagger will be setup between the EMF Canal and double barrel box culvert for truck haul.

Right lane closure northbound Power Road for storm drain installation from Gavelston to Ray Road.

Northbound right lane closure on Power Road from Galveston to Ray for storm drain installation.

 

 

Project Schedule

 

Construction on this project began in June 2012 and is expected to be completed by April 2014.

Project Details

 

This project is a partnership between the City of Mesa, the Town of Gilbert, and the Maricopa County Department of Transportation (MCDOT), with Mesa acting as the lead agency for design, right-of-way acquisition and construction.

Power Road is a major arterial street, which currently has two lanes of traffic in each direction.  This project is approximately 2.7 miles, beginning on the south side of the interchange with the Santan Freeway, and ending at the north side of the Pecos Road intersection. The proposed improvements include widening the road to three lanes in each direction with a raised median and full intersection improvements at Ray Road and Williams Field Road.

 

Project Funding

 

GMP #1 - The recommended total award amount for this project is $2,606,053.77, based on a GMP of $2,369,139.79 plus an additional $236,913.98 (10% allowance for change orders). The Maricopa Association Regional Transportation Plan (MAG RTP) shall pay approximately 70% of the total cost of the project.  The remainder of funding is available in FY 11/12 Streets Bond Program.

GMP #2 - The recommended total award amount for this project is $31,489,798.19, based on a GMP (GMP No. 2) of $28,627,089.26 plus an additional $2,862,708.93 (10% allowance for change orders). The Maricopa Association of Governments Regional Transportation Plan (MAG RTP) is responsible for approximately 70% of the total cost of the project, which is estimated to be $15,477,938.00.  The City of Mesa, Town of Gilbert, and MCDOT will fund the remaining 30% of the total project cost, which will be approximately one-third each.  Therefore, Mesa’s share will be funded through the FY 11/12 Streets Bond, Wastewater Bond, and Gas Bond Programs. 

 

 

 

 

 

Project Location Map

Construction Progress Photos

Road Closures and Lane Restrictions

Business Promotional Page

Engineering Home

Find us: mctraffic  Facebook Icon  Twitter Icon

 

Open during Construction

The businesses listed below are participating in our Shop Mesa program and are offering some great construction specials! Be sure to check them out!

Burrito Shack

Midfirst Bank

Storage Solutions

Optimal Spine & Health Center

Texas Road House

The UPS Store

Williams Landing Apartments