Project Name: Greenfield Road (Baseline Road to Southern Avenue)
Current Phase: Construction
Contract Amount: $6,263,538.00
Estimated Completion: 180 Days (June 2010)
Traffic Update:
Greenfield Road will be restricted to one lane in each direction from Southern Avenue to Baseline Road until June, 2010 for roadway improvements.
Description:
With traffic from the Superstition Freeway and recent development, Greenfield Road needs to be improved to accommodate traffic growth. The Greenfield Road interchange with US-60 is the only interchange from Mesa's west City limits to Power Road that still has only one left turn lane in each direction to enter the freeway. This project is a Regional Transportation Plan project to mitigate traffic delay and congestion and enhance safety. Specifically this project will widen Greenfield Road to a six lane arterial with a raised median and add dual left turn lanes to enter US-60 for northbound and southbound.