Show/Hide

Elliot Road and Signal Butte Road Improvement Projects

Print
Press Enter to show all options, press Tab go to next option

Elliot Road Waterline - Sossaman to Signal Butte Road

Project Details

Kinkaid Civil Construction has been awarded the project to construct improvements to the water transmission system in the southeast valley.

Project Schedule/Updates

UPDATE: July / August, 2018

PROJECT COMPLETED!

CAP Raw Water Pipeline Project

Project Details

Garney Construction was awarded the Construction Manager at Risk (CMAR) to install a 54-inch pipeline that will extend along Elliot Road from Signal Butte Road to the east for approximately three miles. This pipeline will ultimately provide up to 53 million gallons of water per day to the Signal Butte Water Treatment Plant.

Project Schedule/Updates

UPDATE: July, 2018 / August, 2018

Garney Construction is really making progress - all underground piping on the first phase of the project has been completed!

NEXT UP… 

The contractor is finishing up the final phase of this project - the Elliot Road Improvements portion. This phase includes roadway work, new medians and sidewalks with miscellaneous landscaping on Elliot from Signal Butte to Meridian Road. Below are the paving dates and lane restrictions that will be in place until the end of July:

July 13th - Elliot Road will be restricted to one lane with a flagman from approximately Parkwood to Mountain Road to complete the surface course asphalt. These restrictions will be in place after 8:30am - expect delays!

July 16th - The contractor will be working on pavement patches from Signal Butte Road to the entrance to the Signal Butte Water Treatment plant. During this work LEFT TURNS WILL BE PROHIBITED for east and westbound traffic at the Signal Butte and Elliot Road intersection. 

July 18th - The contractor will place a slurry seal on the north side of Elliot Road from Mountain Road to Meridian. Traffic will be restricted to one lane in each direction.

July 19th through July 26th - The contractor will flip traffic to the north side of Elliot Road and begin working on the south side of the roadway. From July 19th through July 24th - LEFT TURNS WILL BE PROHIBITED for east and westbound traffic at the Signal Butte and Elliot Road intersection. Left turns will be restored on July 25th as the contractor completes adjustments and striping.

July 26th - Paving Complete!

A new park is planned for the area east of the new Water Treatment Plant on the northeast corner of Signal Butte and Elliot Road. The City hosted a public meeting on December 13,2017 allow residents to view renderings of the proposed amenities. Below is a link to view the renderings that were presented at the meeting.

Park Concept Plans

If you have any questions, please contact Rene Powell, Michele Arrollado or Lucy Lopez at 480-644-3800.