To minimize disruption along this high-traffic corridor, construction segments will be phased.
Phase 1 – Northbound Widening
Construction will begin at Ellsworth Road and Germann Road, progressing northward in approx. 1-mile segments at a time. This is to widen the roadway from two lanes to three lanes in the northbound direction. Southbound lanes will remain unaffected during this phase when possible.
Phase 2 – Southbound Widening
After completing northbound improvements, crews will shift to the southbound lanes, starting at SR-24 and moving south to Germann Road. Northbound traffic will remain open with minimal restrictions during this phase.
Phase 3 – Median and Landscape Improvements
The final phase will focus on center median modifications and landscape/irrigation enhancements.