McKellips Relief Sewer Project No. CP0619NS12

  • Project typeUtility Improvement
  • Project scheduleConstruction began in mid-April 2025 and will be completed by August 2026.
  • Contractor nameB&F Contracting

Overall Project Area Map(PDF, 4MB)

Project Description

Existing sewer mains have reliably served this area of Mesa for over 50 years. However, with continuous growth additional sewer capacity is needed. To address this, Mesa has contracted with B&F Contracting to install a new 15-inch diameter sewer. Accomplishing this task will require updating and/or relocating sections of existing utilities like water and gas lines and some storm drains.project area map

To reduce roadway closures/restrictions, the sewer line installation and utility relocations will be done in various phases; at times, work will continue through the night or on weekends where possible. Due to the recent water main break in 2024 and having an overlapping work area, the reconstruction of the Gilbert and McKellips intersection has also been incorporated into this project after the utility work completes.

Project Phasing

Gilbert/McKellips AreaWork crews are actively installing a new sewer line and associated manholes on McKellips Road between Harris Drive and Gentry Drive (east of Gilbert Road). The sewer alignment is located in the center of the roadway, and traffic has been routed around the active work area. Lane restrictions are required during construction and are restored as soon as possible as work progresses. Sewer installation in this area is anticipated to be completed by the end of March 2026.

Following completion of the sewer work, intersection improvements at Gilbert and McKellips will begin. This work will include installation of new ADA-compliant corner ramps, as well as removal and replacement of asphalt extending several hundred feet in all directions from the intersection. Electronic message boards will be used to provide advance notice of upcoming traffic restrictions.

project area map

 

Utility Relocations - Stapley/McKellips Area

To accommodate the new sewer line, existing utility conflicts must be removed and relocated. While this work typically occurs as construction progresses, an unforeseen utility conflict was discovered just east of the McKellips and Stapley intersection.

This conflict was resolved in January, and sewer line installation in this area has resumed. Work is expected to be completed by late February 2026.

Project Phase Tracking:

• Install new line sewer on Stapley Drive – Brown to McKellips (Completed)
• Utility Relocation Work – East side of McKellips at Stapley (Completed)
• Install new sewer line on McKellips, just east of Stapley (Duration: 2/2/26 to 2/20/26)
• Install new sewer line on McKellips – Harris to Gentry, east of Gilbert Road (Completes end of March 2026)
• Repair Gilbert/McKellips Intersection (April - August 2026)