Fire Station 205 at Diamond Avenue and Greenfield Road will be deconstructed and rebuilt to prepare for increased call volume and operational efficiencies. During construction, firefighters assigned to Station 205 will respond to calls from a nearby facility to ensure continued service to the area.
Anticipated Construction Timeline
Fall 2025 – Site prep and demolition Winter 2025/Spring 2026 – Foundation and utility work Summer/Fall 2026 – Building structure takes shape Winter 2026/Spring 2027 – Interior finishes, equipment install, final inspections