Projects

Print
Press Enter to show all options, press Tab go to next option

 

 Problem_Button

 

Signal Butte water treatment plant
Project No. C01600
Info/Contact
The City of Mesa has awarded this project to Sundt Construction, Inc.
Schedule
It is expected the Water Treatment Plant will be completed in October 2018.
Details

The Signal Butte Water Treatment Plant will have a robust process design that employs multiple process for maximum operational flexibility and treatment of varying raw water qualities. The plant will incorporate safe and reliable water treatment technology with automation and quality monitoring systems to protect the public health. The Signal Butte Water Treatment Plant will integrate with park planned on the surrounding City owned property. Today the site includes landscaped berms with desert plants and decomposed granite that were added with the initial construction of the water treatment facility reservoir and pump station (currently in operation). Storm water retention areas were constructed east of Signal Butte Road. In addition to the architectural improvements internal to the water treatment plant site, the current park concept includes a first phase of construction with a mix of passive and active recreational uses such as pedestrian and bike paths through the park and along Siphon Draw Wash. The surrounding berms, desert trees and shrubs will help screen the water treatment plant in addition to the eight foot block wall surrounding the water treatment plant.

 

State-of-the-art technology is used to generate a "bleach" solution on site for chlorination to reduce hazardous chemicals stored at the plant. Water is recovered from the residuals captured in the process and recycled into drinking water to conserve our precious resource in the desert. In addition, CAP water comes from a sustainable source of supply: surface water and snow melt into the Colorado River.

 

Bringing this third renewable water supply source into the City of Mesa will help ensure the City can continue to attract sustainable businesses and neighborhoods and reduce ground water dependence in the area. The new 24 million gallons per day treatment plant will have a smaller footprint than other conventional water treatment process and is designed to be expanded to a total capacity of 48 million gallons per day.

 

During construction a 160 foot tower crane will be used for moving materials and formwork for the main treatment complex located in the center of the site. Construction will occur between 6:00 am and 8:00 pm, Monday through Friday, however there will be times with the Contractor will be operating under a temporary exemption with approval from the City to allow for placement of concrete when environmental and construction conditions require it.

 

Renderings

 

Funding
The total authorized amount recommended for this project is $127 million.  Funding is provided by 2014 Water Bonds.
main and Lindsay road sewer replacement
Project No. cp0383-0006rb
Info/Contact

The City of Mesa has awarded this project to Achen Gardner.

 

Schedule
Construction began late August 2018 and will last for approximately four months.        
Details

Achen Gardner Construction has been awarded the contract to replace the existing sewer main line and install new 12” and 15” sewer line in Main Street from Lindsay Road to just east of Val Vista Drive.

 

Funding
The Construction contract is in the amount of $1.9 million. Funding is available from the 2014 authorized Wastewater Bonds.  
Roosevelt road improvements, Broadway road to 8th avenue
project no. cp0528 
info/contact   The City of Mesa has awarded this project to AJP Electric, Inc.
schedule  Construction to begin late-August 2018 and be completed within four months. 
details 

The project improvements include new curb and gutter, sidewalks, pavement, street lighting, landscaping, and storm drains. The project also includes the abandonment

of the existing sewer line along Roosevelt Road and a new sewer main will be installed in the roadway.

 
funding 

The Construction contract is in the amount of $1.3 million. This project is funded by Local Street Sales Tax and 2014 authorized Wastewater Bonds.  

 

Elliot road Tech corridor, Signal Butte road to Ellsworth road
Project No. Cp0571bond
Info/Contact
The City of Mesa has awarded this project to Nesbitt Contracting.
Schedule
Construction began May 2018 and will be completed by February 2019. 
Details

Roadway widening on Elliot Road from Ellsworth Rd to Signal Butte Road.  New roadway construction of Crismon Road. Also includes landscape, irrigation, water and sewer extensions, lighting, signing, marking, signal improvements, directional signs and a monument sign.

 

Project Updates

Funding

The Construction contract is in the amount of $9.6 million. Funding is available from the 2013 authorized Street Bonds and Transportation Funds.

Horne utility improvements, Horne between southern avenue and 6th avenue
project no. cp0366  
info/contact   Under Design
schedule   To be determined
details  The City of Mesa is proposing to construct utility and drainage improvements on Horne Avenue between Southern Avenue and 6th Avenue.  The existing water and gas lines are from the 1960s and are undersized. This project includes the installation of a new 16” water line and a new 4” gas line. Also, a new chemical feed line will be installed on the existing sewer main to provide increased corrosion control.
funding 

This project is funded by Local Street Sales Tax and 2014 authorized Water, Wastewater and Gas bonds.  

plan set 'a' baseline road improvements, 24th street to consolidated canal, project no. CP0658
plan set 'b' Val Vista Drive Roadway Improvements, Baseline Road to us60, Project no. cp0105
info/contact To be determined
Schedule Coming Soon - Early 2019
details

Plan Set 'A' - Approximately 0.90 mile of roadway improvements on Baseline Road from just east of 24th Street to the Consolidated Canal. These improvements will provide three lanes in each direction, bike lanes, pavement reconstruction, raised center medians, drainage structures and facilities, landscaping and street lighting. Other improvements include the installation of a 12-inch water line, replacement of curb, gutter, sidewalk, driveway and handicap ramps in various locations in response to the Americans with Disabilities Act (ADA).

 

Plan Set 'B' - Approximately 0.50 mile of roadway reconstruction improvements on Val Vista Drive from Baseline Road to US60. Improvements include, mill and overlay, including the addition of a 3rd northbound lane starting at Baseline Road for approximately 600 feet, landscaping, irrigation, gas line relocation, installing a new gas regulator station with SCADA system, and traffic signal improvements.

funding To be determined

southern avenue improvements, greenfield to higley Road
project no. cp0700
info/contact Contractor to be determined
schedule Construction anticipated to begin March 2019 and will last approximately nine months.
details The City of Mesa plans to improve Southern Avenue between Greenfield Road to Higley Road. Improvements include, intersection improvements (widening) at the intersection of Southern Avenue and Higley Road. Other improvements include new raised

medians at the intersection of Southern and Higley, curb, gutter, sidewalks, new streetlights and traffic signals.

funding Funding for this project is available from Arterial Life Cycle Program (ALCP).

Mesa Drive Improvements, Phase 2
project no. c01400
info/contact The City of Mesa has awarded this Construction Management at Risk (CMAR) project to Haydon Building Corporation
schedule Construction is anticipated to begin early 2019 and will last for approximately18 months.
details

The City of Mesa plans to improve Mesa Drive from 8th Avenue to Main Street and Broadway Road from Wilbur to Lesueur.  Project improvements include; adding drainage structures and facilities, and replacing water and gas mains in Broadway Road from Wilbur to Lesueur and on Mesa Drive from Broadway Road to 2nd Avenue.  Pavement reconstruction, raised center medians on Mesa Drive and Broadway Road and bike lanes. Replacement of curb, gutter, sidewalks, driveway’s and handicap ramps in various locations. Install new landscaping.Install new street lighting and traffic signals.  Overhead electric will be underground on Mesa Drive from 8th Avenue to Broadway Road and will eliminate aerial crossings up to Main Street. Relocate a few poles on the north side of Broadway Road, east of Mesa Drive for intersection widening. There will also be a portion of SRP irrigation line replaced on Mesa Drive, south of Broadway Road.

 

Exhibits and Renderings from Public Meeting:

funding Funding for this project is available from the 2013 Street bonds and 2010 Gas, Electric and Water/Wastewater bonds.


southern avenue and Stapley drive intersection improvements
project no. cp0800
info/contact Under Design
schedule The project is estimated to begin early 2020 and be completed within one year.
details The City of Mesa plans to improve the intersection of Southern Avenue and Stapley Drive. The improvements include widening the intersection to include three

through lanes on Stapley Drive, a dedicated right turn lane on eastbound Southern Avenue, and bicycle lanes. Other improvements include new raised

medians, curb, gutter, sidewalks, new streetlights and traffic signals.

 

Exhibits and Renderings from Public Meeting held on August 29, 2018:

 

Project Map 

 

Southern Avenue Roll Plot

 

Southern Avenue Layout

 

Stapley Drive Roll Plot

 

Stapley Drive Layout

 

funding Funding for this project is available from Highway Safety Improvement Program (HSIP), Arterial Life Cycle Program (ALCP), and Local funding.





Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer